The project, one of President Bola Tinubu’s flagship infrastructure initiatives, commenced in March 2024. The minister’s comments have renewed debate over how the government intends to determine the full cost of the highway and account for the financial commitments involved in completing the entire route.
Umahi explained that although the coastal route had been conceived decades ago and gazetted in 2006, he had not found a complete engineering design or comprehensive soil-investigation documents covering all 750 kilometres in the ministry’s records.
He said detailed engineering designs were being developed for individual sections after environmental assessments and soil investigations established the technical requirements of each area. According to him, variations in terrain, soil conditions, bridges and road configurations make it inappropriate to apply one average construction cost to the entire route.
The minister also challenged estimates placing the total cost of the project at about ₦15 trillion, questioning how the figure had been calculated before the designs and costs of all sections were finalised.
To defend the cost of the initial stretch, Umahi compared part of the Nigerian project with a 47.47-kilometre coastal road in the neighbouring Republic of Benin, which he said cost approximately ₦1.06 trillion.
He cited an estimated cost of about ₦7.5 billion per kilometre for a three-carriageway configuration before adjusting the calculation for a standard two-lane carriageway. Based on an exchange rate of ₦1,330 to the dollar, he put the adjusted estimate at approximately $5.5 million per kilometre.
However, the minister stressed that road specifications and construction requirements differ, making direct comparisons between projects difficult without accounting for their individual features.
Umahi also addressed concerns about the highway’s environmental approvals. He said construction began after the ministry obtained provisional Environmental and Social Impact Assessment approval, adding that assessments and related requirements were being handled in phases rather than through a single document covering the entire route.
He maintained that the first 47-kilometre section had received final environmental approval, while work on other sections would proceed alongside the relevant technical and environmental processes.
The project has faced public scrutiny over its cost, route, environmental implications and procurement arrangements. The Federal Government has defended the highway as a major transport corridor expected to improve connectivity and support economic activity across Nigeria’s southern states.
Umahi also clarified the government’s plans to connect the coastal highway to the existing East-West Road, following controversy over whether the original route had been changed.
He insisted that the planned connection would not replace the original alignment. Instead, he said, the government intended to construct an additional spur linking the coastal highway to the East-West Road through Edo State.
The minister described his earlier use of the word “diversion” as a slip of the tongue, maintaining that the original route through Lagos, Ogun, Ondo, Edo, Delta, Bayelsa, Rivers, Akwa Ibom and Cross River states remained intact.
He said the additional connection would provide an alternative route for motorists and complement plans to reconstruct deteriorated portions of the East-West Road, some of which he said were vulnerable to flooding.
According to Umahi, design work on the proposed connection is ongoing. He maintained that the additional road link should be treated as a separate development connected to the coastal highway, not as a replacement for the original 750-kilometre project.
The absence of one comprehensive engineering design does not, by itself, establish that no designs exist for sections already under construction. However, the minister’s disclosure raises questions about the timeline for completing the remaining designs and establishing a reliable overall cost for the project.
Reporting by TalkNaijaMedia