The governor said the airport could improve connectivity, encourage investment and support commercial activities across Kogi State. He argued that the state’s proximity to major economic centres, including the Federal Capital Territory, made improved air transport infrastructure a potential advantage for businesses and residents.
Ododo credited the Tinubu administration with approving and supporting the project, saying federal backing for infrastructure at the state level demonstrated recognition of the development needs of subnational governments.
He pledged that his administration would continue monitoring construction to ensure compliance with the required standards and project timelines. He also expressed hope that the airport would reach an advanced stage of development in 2027, although he did not announce a confirmed completion or operational date.
Responding to criticism about the project’s feasibility, Ododo invited sceptics to visit the construction site and assess the work themselves rather than rely on speculation.
He said construction equipment was operating at the site and maintained that the project’s progress could be observed directly.
Providing an update, Sun Yishi, project manager at CCECC Nigeria Limited’s Kogi State project office, estimated that construction was approximately 20 per cent complete. He said the current phase focused mainly on earthworks for the runway and its associated safety areas.
According to Yishi, the work involves excavation, filling, laterite placement and ground preparation before the project can move into subsequent pavement construction.
Adebayo Adidipe, lead consultant and architect with Arcade Consultants Limited, gave a slightly higher estimate, putting overall completion at between 20 and 25 per cent. He expressed confidence in the progress and commended the state government and officials of the Ministry of Transportation for responding to issues raised by the project team.
The difference between the two estimates reflects the figures provided by the project manager and lead consultant during the inspection; no independently audited progress assessment was cited in the reports reviewed.
The airport project is expected by the state government to strengthen transport links and support future economic activity. Its eventual impact, however, will depend on the completion of construction, operational readiness, supporting infrastructure and the availability of airline services.
For now, construction remains ongoing, with earthworks forming a major part of the work reported by the project team.
Reporting by TalkNaijaMedia
Reader Comments (0)
No comments yet. Be the first to share your perspective on this report.