Residents of several communities in the Federal Capital Territory (FCT), Abuja, have expressed frustration over prolonged electricity outages, saying the disruption has affected businesses, water supply, food preservation, and other essential daily activities.
The complaints come amid reports of technical problems affecting electricity transmission infrastructure, with the Transmission Company of Nigeria (TCN) and Abuja Electricity Distribution Company (AEDC) identifying separate issues linked to supply interruptions in parts of the territory.
In Kubwa, a resident, Fatima Muhammad, said the blackout had affected both her household and her baking business. She explained that she had run out of water because she could not operate her pumping machine, while some of her baked products had spoiled due to the lack of electricity.
Muhammad said the situation had caused financial losses and made it difficult to carry out routine activities that depend on a reliable power supply.
Other residents have also taken to social media to express dissatisfaction with the duration of the outages and the pace of communication about restoration efforts.
A user identified as Peace Kanu PIAK reported that Dutse had experienced two days without electricity before she saw an update on the situation. She appealed to TCN’s technical team to speed up efforts to restore supply.
Another user, Christian, criticised AEDC over what the user described as five days without electricity, arguing that customer complaints should be addressed as quickly as updates are published.
Residents in other areas also reported longer interruptions. A social media user identified as Nazeerah said parts of Area 8, Garki, had been without electricity for three weeks, describing the situation as overwhelming.
Some customers on Band A tariffs also questioned the consistency of their supply, alleging that they were experiencing repeated periods of electricity followed by outages despite paying for a higher service category.
Complaints also came from Bwari, the Nigerian Law School area, Ushafa, Bmuko and Dutse, where residents called for urgent intervention by the relevant electricity authorities.
According to the report, landlords’ associations in Ushafa, Dutse and Kubwa were considering a protest for Monday if the situation remained unresolved. The proposed action reflects growing frustration among residents, although the reported plan does not establish that a protest has taken place.
TCN had earlier announced a planned interruption to electricity supply in parts of Abuja to allow maintenance work at its 132/33kV Kubwa Substation. The company said AEDC would be unable to receive supply for customers in Kubwa, Bwari, Army Resettlement, parts of Dutse Alhaji and neighbouring areas during the maintenance period.
In a separate notice, AEDC attributed another disruption to a technical fault on the 330kV Shiroro–Katampe transmission line. The company listed Garki, parts of Apo, Asokoro, Wuse Zones 1 and 2, Wuye, Jabi, Utako, Jahi, Life Camp, Gwarinpa, Kubwa, Dawaki, Dutse, Dei-Dei, Suleja and adjoining communities among the affected locations.
AEDC said TCN’s technical team was working to resolve the fault and restore stability, assuring customers that supply would return once the transmission line issue was cleared.
The reported maintenance and transmission-line fault provide explanations for some of the interruptions, but they do not independently confirm the cause or duration of every outage reported by residents. The complaints about supply lasting several days or weeks also highlight the need for clear, area-specific updates from the relevant authorities.
The situation has renewed attention on the impact of unreliable electricity on small businesses and households. For businesses such as bakeries, outages can lead to spoiled products, interrupted production and additional operating costs, while households may struggle to pump water, preserve food and carry out routine tasks.
The development comes weeks after Minister of Power Joseph Tegbe spoke about reported improvements in electricity supply in some parts of the country. Speaking at the commissioning of a 3-megawatt solar hybrid project at Yakubu Gowon University, Abuja, in September, Tegbe said some consumers who had previously experienced prolonged outages were reporting up to 18 hours of electricity daily.
The project was designed to improve power supply to essential university facilities; however, it does not demonstrate that electricity supply has improved consistently across all communities in the FCT. (Rural Electrification Agency)
As residents await restoration, attention remains on the efforts of TCN and AEDC to resolve the reported technical problems and provide timely information to affected communities. For those whose businesses and households have been disrupted, a dependable return to electricity supply remains the immediate priority.